Design

residential drafter

Just like with our Custom Homes, we have the knowledge and ability to design your New Barndo, in house!

When utilizing our design capabilities, you should expect a healthy flow of information. Our process includes the following:

  • Initial Consultation and inspiration review.

  • 50% review

  • 75% review

  • Final touch ups and exterior facade selections,

line item estimate
custom design; design build

Estimating

When shopping Builders, you probably hear a “square foot price”, quite often. In many cases, this pricing is “Subject to Change”, and quoted low as a gimmick to get you in the door..

We prefer to quote high value estimates that include measurements, and all of your selections (with realistic budget numbers).

Our Estimating Process includes:

  • Initial Budget Discussions- Grade of finishes and fixtures.

  • Selections Type- Flooring, counters, cabinets.

  • Material and Labor takeoffs

  • Budget and Estimate Review

    This process may repeat itself as often as it takes as we work to include your must-haves and wants into our package.

Construction

Following Contract signing, Construction can begin!

A typical Barndo-build should follow this format:

  • Site prep & Land Clearing (3-5 days)

  • Form boards and Plumbing Rough (3-5 days)

  • Pour day!! (8-12 hours)

  • 2 week layover while our new pad hardens.

  • Steel Frame, Sheet metal, Doors and Windows (1-3 Weeks)

  • Interior Frame (1-2 Weeks)

  • Mechanical, Electrical, Plumbing Top-out Bringing everything up into the frame (1-2 Weeks)

  • Spray Foam Insulation Our typical includes 1” Closed Cell all around, with 3.5” Open Cell encapsulating the living space. (1-3 Days)

  • 3 day layover for the Spray Foam to off gas properly

  • Sheetrock and texture- Priming the walls (1-2 Weeks)

  • Cabinet Measure (1 Day)

  • Trim Carpentry and Closets (1-2 Weeks)

  • Tile Work (1-2 Weeks)

  • Cabinet Install (1-2 days)

  • Flooring Depending on type (3-5 Days)

  • Paint 2 coats after primer (5-7 Days)

  • Counter Tops Install (1 Day)

  • MEP Trim out Installing fixtures throughout the home (5-7 Days)

  • Paint and Trim Touchups and Punch list (1-2 Weeks)

Custom barndominium
foundation
Steel construction, weld up steel, red iron build
custom front entrance
  • On average our projects take between 5-7 months to complete.

  • We have a history with various Lenders, as well as experience with the approval process for New-to-us Lenders!

  • We can service this request as well!

  • Vapor and humidity problems arising after a home is insulated is generally caused by an improperly sized or equipped HVAC unit. It is imperative to not “Over size” your unit, or forget to install fresh air intakes.